Minery

ICO Ended
387 days 17 hours ago

Description

What is Minery? Minery represents a different solution. It combines large mining compounds, low entry criteria, high quality hosting, a service center in close vicinity and one of the lowest electricity rates in the whole world. We procure the hardware, install and set it up. In case of breakdowns we repair it right on the spot. These characteristics make the Minery project highly efficient and convenient. Where? When choosing location for mining, the ideal placement will offer both low electricity rates and low average annual temperature. Russia is one of the best countries to place a mining farm. Our mining compounds are located in the cities of: Bratsk, Ust-Ilimsk, Irkutsk. Average annual temperature –2°C. These climate conditions allow us to use highly effective heat transfer and cooling system for the miners and ultimately reduce hosting expenses. Power sources Our power supplier is Bratsk Electric Grid Company, JSC (BEGC) which is among the largest in the Irkutsk region.

 

General
ICO Dates
01 Jul 2018 - 30 Sep 2018
Whitelist / KYC
KYC
Country
Russian Federation
Ticket
MNRY
Token Type
ERC20
Available for Sale
Financial
Pre sale Price
1 MNRY = 1 usd
ICO price
1 MNRY = 1 usd
Accepting
ETH, BTC, Fiat
Hard Cap
55M $
Tokens for sale
47,850,000
Bonuses
Presale Up to 20%

Week 1-2 Up to 10%

Week 3-4 Up to 8%

Week 5-6 Up to 6%

Week 7-8 Up to 4%

Week 9-10 Up to 2%

from Week 11 Up to 0%

  • 1
    March 2018

    Purchasing real estate, securing land rights, procuring hardware, continuing software development for mining compound management.

  • 2
    April 2018

    Engineering, securing authorizations and approvals.

  • 3
    May 2018

    Ordering electrical equipment, beginning groundwork, laying foundations for facilities 2-5. Facility 1: finishing work begins, internal supply lines installation.

  • 4
    June 2018

    Facilities 2-5: finalizing groundwork and laying the foundation. Facility 1: finishing works, installing ventilation.

  • 5
    July 2018

    Facilities 2-5: construction works, internal supply lines installation begins. Facility 1: finalizing engineering and finishing works, commissioning preparations, transformer substations installation.

  • 6
    August 2018

    Facilities 2-5: finalizing engineering, commissioning preparations, transformer substations installation. Facility 1: finalizing transformer substations installation, utility connection and commissioning.

  • 7
    September 2018

    Facilities 2-5: finalizing transformer substations installation, utility connection and commissioning. Facility 1: hardware installation and set-up. Finalizing software development for mining compound management.

  • 8
    October 2018

    Facilities 2-5: hardware installation and set-up, token issuance.